Squeezed between
Snowstorms and the Easter Holiday
The
inauguration of the hangar project was set for the 27th of April 2022
but there was so much to do before that date. We needed to connect
central heating, water, electricity, telephones and LAN to the hangar
and also hook it to the main sewage system.
Successive snowstorms of the long winter this year delayed our work.
Heavy machinery can only work on firm ground. The land around the hangar
was drenched with water from rain and melting snow. We would get a few
days of sunshine raising our hopes for starting the work when another
snowstorm would start.
Trainers of the JLSS electricity workshop with the third year Dual
System students were working on the electric wiring and installations
inside the hangar.
Trainers of the carpentry workshop with their students were making the
blackboards and hanging them in addition to hanging the large TV screens
in each new classroom. Wading through the mud to reach the new hangar
was extremely annoying but they all pressed on with work.
The work we had to do was squeezed between successive snowstorms and the approaching
Easter holiday just before the inauguration date.
Finally, after a few days of sunshine, Mr. Shadi Naim and his team
succeeded in installing the central heating system and hooking it to the
boiler room of the nearby Car Mechanics building. They also connected
the hangar to the main water supply and the public sewage system.
Mr. Shadi Naim and his team safely moved the heavy machinery from the
old carpentry workshop to the new one on the ground floor of the hangar.
Our electricity team of trainers and students connected the hangar to
the main electricity grid. They also connected the cables for telephones
and LAN and pushed on with the electric installations inside the hangar.
Mr. Mohammad al-Khodor and his team completed the partitions, tiling,
and wall paneling of the classroom floor and the facilities of the
ground floor.
The new classroom furniture was delivered on time by Fleifel Classroom
Furniture Company.
The photocopier kindly donated by the alumni association in Lebanon was
also delivered. We thank the alumni association in Lebanon for this
donation.
Everything was beginning to look really nice, but the area outside
needed a lot of work before the inauguration.
The Industrial Mechanics team of trainers and students started working
on building the fence around the new extension of the school campus. It
was a mammoth task that we thought will not be completed in time.
The plot of the hangar was bare land with no trees. We wanted to plant
trees to bring this extension of the campus to harmony with the rest of
the school campus.
We couldn't start planting trees before the fence was completed.
Whatever is planted would be destroyed by the goats that daily graze
every open green area with total disregard of herders to private
property.
We only had a few days before the Easter holiday.
The old Schneller spirit had to be resurrected otherwise the work would
not be completed in time for the inauguration. The only way to finish
the fence was for the whole vocational department, trainers and
students, to work on the fence.
Although many trainers and students were fasting for Lent or Ramadan,
they all headed to the plot of the hangar dividing into many teams
working on different parts of the fence at the same time. They took
shifts in the heat of the sun relieving each other to get the job done.

Finally, after three days, the fence was completed, but hundreds of
trees were ready for planting.
The plot is the shape of a triangle with the South side along the road
to the farm, and the other two sides to the East and West. Cypress,
pine, and cedars were planted on the East and West sides and the open
areas, and red wild prune trees and yellow jasmines were planted on the
South side along the road to the farm.
Class after class, from both the academic and vocational departments,
assisted by staff of the Maintenance Department planted 250 Cypress
trees, 50 pine trees (seed producing), 7 cedars, 25 red wild prune trees
and 25 yellow jasmines.
Three cedar trees were kept for planting by our partners on the
inauguration day.
In addition to that we also planted 70 original Lebanese olive trees
(ABOU SHAWKEH) in other locations of the school.
We will continue the tree-planting program even after the inauguration
until all the trees we have are planted. Every student and member of
staff in JLSS will have planted at least one tree this year.
Our students not only learn to love and protect nature, this year each
student will be proud that the JLSS campus has at least one tree she/he
planted. They will know exactly where these trees are.
The maintenance department installed an irrigation system to guarantee
that all trees will be watered adequately until they can survive on
their own.
Sadly, some workers on our project, especially from one big contractor,
had no sense of cleanliness. Although we removed a few truckloads of
garbage from the area after some of the neighbors complained, there was
still a lot of garbage around. Our trainers and vocational students
organized a cleaning campaign around the area of the project removing
all the garbage that was left behind.
Mr. Mohammad al-Khodor and his team will work on the concrete road and
pavement over the Easter holiday. With that the project will be complete
and ready for the inauguration on the 27th of April.
A big thank you to everyone who worked on this project. Every trainer,
student, or member of staff can be proud of the wonderful achievement of
this amazing group effort. We also thank all the contractors and
engineers who worked on this project (Dalal Steel and Yehya Daher
Engineering).
A huge thank you goes to the supporting body of JLSS, our German
partners EVS/EMS, for being the main supporter of this project not only
in financing the actual construction but also the purchase of the needed
school furniture.
We also thank our Swiss partners SVS and American partners LBMS
(Lutheran Board for Mission Support) who generously supported the needed
school furniture and other aspects of the project.

These were not the only JLSS events during those challenging days. Ms.
Josephine Mansour reached retirement at the end of March 2022. She had
been working in JLSS since 1996. A special celebration was held on
Thursday 7 April in Maria Schneller Hall to thank her for her long years
of outstanding service. Attending was the whole Schneller team of
trainers, teachers and members of staff from all departments. Rev.
Haddad thanked her for her wonderful work with JLSS children emphasizing
her refined, gentle, calm yet disciplined character. No wonder she is
loved not only by her students but also her colleagues.
It was also the time of Easter and the fast of Ramadan. Classes and
boarding homes were decorated nicely for both Easter and Ramadan.
The kitchen staff did every thing they could to support fasting students
with the special meals of SUHUR and IFTAR.
We also needed to buy the chocolate eggs and Easter cakes to distribute
to students after the Easter celebration of the boarding department.
This was a challenging task this year as chocolate is now very expensive
in Lebanon due to the enormous drop in the value of the Lebanese
currency. This was not the only challenge. When we asked for samples of
chocolate eggs and we tried them, we immediately realized the effect of
the slow turnover on such items in Lebanon now. The chocolate did not
taste good but was rather old. The only good chocolate we found was from
the most famous Lebanese sweets-shop in Chtaura which was expensive. We
still bought the needed chocolate eggs and Easter cakes for all our
boarding students to make sure our celebration this year will not be
lacking in any way.

On the last night before the Easter holiday the boarding department
celebrated Easter in St. Michael's Church with a service of readings and
Easter hymns which was held on Tuesday 12 April 2022 at 6:30 PM.
The special Easter dinner was postponed until after the service to be after breaking the fast. All students were able to enjoy this
special dinner together.
We thank our kitchen staff for their wonderful work and this special
dinner.
The Kindergarten had a special celebration the following day on
Wednesday. Children had an egg-hunt around the kindergarten and a nice
celebration of music, activities, and good food all prepared by the KG
teachers.
School will resume after the Easter holiday Tuesday morning 26 April.
The inauguration of the hangar project will be on the following day:
Wednesday 27 April. It will include an organ and trumpet concert kindly
performed by our dear friend Klaus Schulten accompanied by Britta
Giesecke von Bergh on the trumpet. Both are travelling from Germany
specially for this concert. The concert will be of trumpet music of the
17th century and organ music of the 18th century by J. S. Bach and W. A.
Mozart.
We thank them both for their wonderful kindness and we certainly look
forward to the concert.
A big thank you and a very happy Easter to everyone.
